Daelim Receives Mechanical Completion Certificate for S-OIL SUPER PKG-1 & 2

DATE 2017.03.15

VIEW 11978

Daelim Receives Mechanical Completion Certificate for S-OIL SUPER PKG-1 & 2


MHC Unit

Daelim received a mechanical completion certificate on the construction of S-OIL SUPER PKG-1 &2 in early March. The S-OIL SUPER PKG project involves the installation, remodeling of main equipment, and new plant construction (HGO) to increase the processing capacity of S-OIL’s plant operated within Ulsan Onsan Industrial Complex.


HGO Unit

Despite many constraints, since the project was carried out within the existing plant, the Plant Business Division achieved mechanical completion with zero accidents within the scheduled construction period as PKG-1 was completed within 23 months of construction kick-off and PKG-2 was completed within 20 months of its construction commencement. Currently, the plant is being operated normally, and Daelim is performing an additional RFCC Slurry Section project.